Hi Builders,
I got this update from Habitat:
Hi Pat,
I need to add more to the schedule. Bill did say there is an entire day for painting doors, door trims, shelves, outside storage room. He said there will be another entire day to install all the hardware: doorknobs, cabinet door handles, etc. Please keep an eye out for those opportunities.
There will be no build day this Saturday, September 3rd, due to Labor Day weekend.
I anticipate this means 9/10 will be finish up painting, and 9/17 will be finishing the project, except for grass, possibly on 9/24. The Wednesday crews may take care of some of this as well.
Have a blessed Labor Day,
Pat