CITY OF TEMPE PAVEMENT PRESERVATION PQI INDEX PROJECT TIMELINES
The Optimist Park area will be under construction through June 2023. Work includes sidewalks, curbs, valley gutters, milling, paving, and landscaping in the right of way adjacent to some properties. This requires keeping the streets clear.
While the window of work is long and broad, the city asks that there is no parking on Libra Drive surrounding the Church Property from:
January 10th thru March 6th - Concrete Improvements
March 7th thru May 22nd - Paving
Work hours 7am - 4pm
Concrete pouring 6am
Parked vehicles will be towed
Please pay attention to all signage and barricades. Project dates are subject to change due to weather, equipment or other unforseen issues in the field.