CITY OF TEMPE PAVEMENT PRESERVATION PQI INDEX PROJECT TIMELINES
The Optimist Park area will be under construction through June 2023. Work includes sidewalks, curbs, valley gutters, milling, paving, and landscaping in the right of way adjacent to some properties. This requires keeping the streets clear.
While the window of actual work is broad, the city requests
NO PARKING ON LIBRA DRIVE surrounding the Church Property during:
Concrete Improvements through March 6th
Paving - March 7th thru May 22nd
Work hours 7am - 4pm
Concrete pouring 6am
Parked vehicles will be towed
Please pay attention when all signage and barricades are in place. Project dates are subject to change due to weather, equipment or other unforseen issues in the field.